Crossroads to Hamilton (Spotsylvania 3rd Trk) & New Spotsylvania Station

Scope: To construct approximately 2.5 miles of third track on the CSX right of way from the VRE Crossroads Yard to Hamilton. The project will also construct a longer yard lead to accomodate a new VRE Spotsylvania train station. The design phase is expected to be completed by the end of 2012 at which time the plans will be issued for bidding.

Scheduled Completion: December 2013

Project Budget: $37 Million

Current Status: Preliminary Design