Franconia-Springfield Station Improvements

back to projects list

Project Description

Extending the platforms will better accommodate up to 8-car train consists. All doors will be able to open onto the platform for more efficient boarding and alighting with a reduction in passenger queuing within the train. The current design does not preclude a future third mainline track by the Virginia Department of Rail and Public Transportation.


Project Purpose

The purpose of this project is to provide improved operational flexibility, capacity and reduce dwell times. Proposed and planned future work at this location are consistent with these VRE goals.


Anticipated Project Schedule:

Phase Start Date Finish Date
Development 8/3/2016 11/29/2018
Final Design 10/21/2018 7/24/2024
Construction 7/25/2024 9/23/2026

Current Phase: Final Design

Phase Image Phase Image

Project Cost:

$13,000,000.00

Project Documents

There are no documents for this project.

Latest Updates

  • Project Note 1:
    90% Tunnel Design received on 2/20/24 and distributed for stakeholder review. ~JB 03/05/2024.

  • Project Note 2:
    Stakeholder comments on 60% Tunnel Design being incorporated en route to 90% submittal, due to VRE on 2/19/2024. ~JB 02/07/2024.

  • Project Note 3:
    60% Tunnel Design under review by CSX. Design advancing to 90% simultaneously. ~JB 12/13/2023.