The Broad Run Expansion Project increases the capacity of the Broad Run Maintenance and Storage Facility (MSF) and Broad Run Station to accommodate forecast near-term growth in VRE ridership. The Project includes the following elements: Reconstructed Station Platform - To expand the Broad Run MSF storage capacity, the station platform will shift to the east of its current location. MSF Expansion - The Broad Run MSF will be enlarged to store additional train consists and spare equipment. Two small administrative and employee welfare (AEW) buildings must be demolished to expand the MSF storage tracks. Their functions would be consolidated within a new 6,200 square foot AEW building. The AEW building will include locker rooms, conference rooms, individual offices, and a break area for use by VRE train crews, maintenance staff and security personnel.

Project Purpose

The Broad Run Expansion project will increase the storage capacity at the Maintenance and Storage Facility (MSF) to receive the additional rolling stock that is currently on order to increase the VRE fleet. The increased footprint of the yard will necessitate reconstruction of the existing station and parking Facilities. The old crew office facilities will be replaced by a new Administrative and Employee Welfare (AEW) building.

Anticipated Project Schedule:

Phase Start Date Finish Date
Development 7/13/2015 9/10/2020
Property Acquisition 11/7/2019 4/1/2026
Final Design 8/10/2021 7/1/2026
Construction 12/1/2026 2/28/2029

Current Phase: Final Design

Phase Image Phase Image

Project Cost:

$100,133,891.00

Project Documents

There are no documents for this project.

Latest Updates

  • 10/9/2026
    The project team has begun reviewing shop drawings for the rail turnouts included in the advanced procurement package. We also continue to work through property acquisitions with the City of Manassas and Prince William County. Once the acquisitions are complete, we will be able to obtain permits and move forward with construction procurement.

  • 8/31/2026
    The project team facilitated a coordination meeting on August 21st with representatives from the City of Manassas and Prince William County, both of which serve as Authorities Having Jurisdiction (AHJs) for the Broad Run Expansion Project. The meeting focused on resolving outstanding review comments and discussing the joint jurisdictional approvals necessary to advance the project. VRE also requested updates on ongoing property acquisition efforts being conducted through both AHJs to support project delivery.

  • 8/10/2026
    The project team is coordinating a meeting later this month with both Authorities Having Jurisdiction (AHJs) to secure the City’s and County’s concurrence on the portions of work located within the other jurisdiction. This coordination will support Prince William County’s issuance of the remaining conditional site permit approval.