Leeland Road Station Improvements

back to projects list

Project Description

The improvements will better accommodate up to 8-car train consists. All doors will be able to open onto the platform for more efficient boarding and alighting with a reduction in passenger queuing within the train. The current design does not preclude a future third mainline track as part of the Virginia Department of Rail and Public Transportation's DC2RVA planning study.

Project Purpose

The purpose of this project is to provide improved operational flexibility, capacity and reduce dwell times. Proposed and planned future work at this location are consistent with these VRE goals

Anticipated Project Schedule:

Phase Start Date Finish Date
Development 12/16/2025 8/20/2026
Property Acquisition N/A N/A
Final Design 9/21/2026 9/12/2027
Construction 10/13/2027 3/11/2029

Current Phase: Development

Phase Image Phase Image

Project Cost:

$12,065,300.00

Project Documents

There are no documents for this project.

Latest Updates

  • 9/3/2026
    CSX’s proposed design review agreement and associated force account estimate are being reviewed.

  • 9/3/2026
    VRE resubmitted the Third-Party Right-of-Entry (ROE) application through the VPRA Third-Party Projects Portal.

  • 9/3/2026
    The design team has advanced the project to 60% design and incorporated comments from the Facilities Working Group meeting. The draft 60% plans are scheduled for September 17, 2026, with the final 60% submission scheduled for October 15, 2026. VRE is coordinating with VPRA on two potential site-related matters: (1) a historic interpretive sign at Leeland Road Station, VPRA expected to cover the design and construction costs; and (2) a potential Temporary Construction Easement (TCE) at the PRTC-owned parking lot, which is currently under review by VRE leadership.